What Construction Oversight on a 203(k) Actually Looks Like

Once a 203(k) loan closes, most buyers think the hard part is over. The papers are signed, the contractor has a start date, and the renovation money is sitting in escrow. Then the walls come open, and the house starts telling you things nobody could see on the first walk-through. That is where construction oversight matters, and it is the part of a 203(k) people understand the least. Here is what it actually looks like from the job site.

It Starts With the Work Write-Up

Oversight is only as good as the plan it measures against. Before closing, I prepare the Work Write-Up and Cost Estimate, and HUD requires that I prepare it without using the contractor’s estimate. That independence is the point. The write-up lists every work item, what it should cost, and what “done” means.

After closing, that document becomes the yardstick. Every visit, every draw, and every change gets checked against it. A vague write-up leaves nothing to hold the work to. A detailed one keeps everybody honest, including the contractor, the lender, and me.

What I Check at Each Draw Inspection

HUD requires the consultant to inspect the work for completion and quality of workmanship at each draw request. On site, that comes down to a few plain questions:

  • Is the work item actually finished, not “mostly done”?
  • Was it done in a workmanlike manner?
  • Does it meet local codes and ordinances?
  • Are the building permits on site for the work that was performed?

When the work checks out, I complete HUD form 9746-A, the Draw Request. Both the borrower and the contractor sign it to certify the work was completed in a workmanlike manner. Then it goes to the lender. The lender reviews and approves each draw and releases the money. I inspect and report. The lender cannot approve a draw for work that is not yet complete, so payments are released as the work gets done, not before.

Change Orders: Changing the Plan Without Losing Control

Old houses surprise you. Rotted framing behind the plaster. Wiring that was never going to pass. Or you simply decide halfway through that you want something different. None of that is unusual. What matters is how the change gets handled.

On a 203(k), a change order is the legitimate way to change the plan. When the borrower or the lender asks, I review the proposed change, evaluate the costs, adjust other work items if needed, and put the labor and material costs on HUD form 92577, the Request for Acceptance of Changes in Approved Drawings and Specifications. A change order can raise the cost of the job or lower it.

Three rules keep this from turning into a free-for-all:

  • Nothing starts until the lender approves it. Work on a change order cannot proceed until the lender signs off.
  • Health and safety items go through the same door. If a health or safety problem turns up during the rehab that was not in the original write-up, the lender must make sure it is addressed with a change order.
  • It gets paid when it is finished. Each change order item has to be 100 percent complete before funds for it are released from escrow.

On a Standard 203(k), once the rehab is complete, leftover contingency money can fund additional improvements that were not in the original write-up. That also takes a change order, and the lender has to tell you in writing within five business days whether the request is approved or rejected.

HUD caps what a consultant can charge for this work at $120 per change order request. If the borrower or lender asks for a work item to be reinspected, the cap is $225.

When Something Goes Wrong, the Lender Hears About It

Part of oversight is simply speaking up. HUD requires the consultant to keep the lender informed of the progress of the rehab and of any problems, including:

  • Work stopped for more than 30 consecutive days, or work not progressing reasonably
  • Significant changes from the Work Write-Up made without the consultant’s approval
  • Anything that could affect program requirements or property eligibility
  • Anything that could affect the health and safety of the occupants or the security of the structure

When the lender is told about a disagreement between the borrower, the contractor, or the consultant, HUD requires the lender to step in. And whenever I report something to the lender, you hear about it from me too. Paperwork is key. Communication is even more important. I keep my clients informed, always.

What Oversight Is Not

It is not a home inspection. HUD requires the consultant agreement to say so in writing. It is not the lender’s job, either. The lender approves the loan, the change orders, and every release of money.

And it is not me making your decisions. If hidden damage turns up, I will tell you what it is, what it should cost to fix, and the pros and cons of each way forward. Whether to add it, trade it against something else, or hold off on an elective item is your call. It’s your money. My job is to protect you and keep the project moving toward the finish line on budget.

You can read more about what the consultant handles on a 203(k) file and what your contractor must turn in before closing.

Michigan Inspection Services works 203(k) files across Southeast Michigan and the rest of Michigan, plus Indiana, Ohio, and Pennsylvania. Michael Al has been a Licensed Builder in the State of Michigan since 1994 and a HUD-Approved 203(k) Consultant since 2019, under HUD ID P1984. The work on your house gets checked by someone who has built it himself.

Want to Know What Happens Once the Walls Come Open?

Call before you close and I’ll walk you through how draws and change orders will work on your file.

Call: 248-469-8460

Email: mal@mis203k.com

Schedule a Free Call

Scroll to Top